Skip to content
Tool Corner

Concrete Calculator

Work out how much concrete a slab, footing or pad needs — in cubic metres, cubic yards, bags and tonnes.

Built and verified by Jogeswara, Founder and Engineer, MSc, PMP — Tool CornerMethod and figures checked against the sources listed belowReviewed
Concrete needed
{{ m3Out }}
{{ warn }}
Cubic yards{{ yd3Out }}
Cubic feet{{ ft3Out }}
Approximate weight{{ weightOut }}
20 kg bags{{ bag20 }}
25 kg bags{{ bag25 }}
Ready-mix cost{{ readyCost }}
20 kg bags cost{{ bagCost }}
Material only, using your prices. Delivery, short-load charges, pump hire and VAT are extra.
{{ verdict }}
Next step

What next?

Concrete is one part of the job. These cover the surfaces that follow it.

What your result means

The headline figure is the volume of finished concrete, including your waste allowance. Bag counts assume a standard pre-mixed ballast product — a 20 kg bag yields roughly 0.011 m³ once mixed, which is why the bag count climbs so quickly. Weight uses 2,400 kg per cubic metre, the usual density for normal-weight concrete.

Why this one is different

The volume arrives in cubic metres, cubic yards and cubic feet at once, because the slab is measured in one and quoted in another. A weight figure and a 20 kg bag count sit beneath, which is the decision the number actually feeds: mixing on site by the bag, or ordering a ready-mix load by the cube.

Ordering advice

Running out mid-pour is far worse than ordering too much

Concrete has to be placed and finished as one continuous operation. A gap while you fetch more creates a cold joint — a visible line that is also a structural weak point. That is why every trade adds a waste allowance rather than ordering the exact calculated figure.

Ten percent is a reasonable default on a flat, well-formed slab. Uneven ground, deep footings or awkward access justify more, because the sub-base absorbs more than you expect.

How it works

Volume is length × width × depth, converted to metres first so the result is in cubic metres. The waste allowance is applied on top, then the total is converted to cubic yards, cubic feet, weight and bag counts using standard yields.

How to use this calculator

  1. Pick the unit beside each measurement. They can differ, for example a slab in metres and its depth in millimetres.
  2. Enter length, width and depth — depth is usually the smallest figure.
  3. Set how many identical pours if you have several footings the same size.
  4. Add a waste allowance of around 10%.
  5. Compare the bag count against a ready-mix order. Enter your supplier’s prices if you want the two costed side by side.

Formula

volume = L × W × D × quantity × (1 + waste)

All dimensions converted to metres. Weight assumes 2,400 kg/m³. Yields: 20 kg bag ≈ 0.011 m³, 25 kg bag ≈ 0.0138 m³.

Example calculation

A slab 4 m × 3 m at 100 mm thick with 10% waste:

4 × 3 × 0.1 = 1.2 m³
With 10% waste = 1.32 m³
≈ 1.73 yd³, about 3.2 tonnes
≈ 120 bags of 20 kg — between 1 and 2 m³ it is a genuine toss-up

Frequently asked questions

How thick should a slab be?+

A garden shed base or footpath is typically 75–100 mm. A driveway carrying cars usually needs 100–150 mm over a compacted sub-base, often with mesh reinforcement. Anything structural should be specified by an engineer.

At what point should I order ready-mix?+

Most people switch above about one to two cubic metres. Beyond that the bag count becomes impractical, mixing consistency suffers, and the pour takes long enough to risk a cold joint.

Does the calculator include the sub-base?+

No. Hardcore, sand blinding and any damp-proof membrane are separate. Calculate the sub-base as its own layer using the same length and width with its own depth.

What mix should I use for a domestic slab?+

A general-purpose C20 to C25 mix suits most paths, sheds and patios. Driveways and anything taking vehicle loads usually call for C30 or above, and the supplier will advise on the specification for your use.

How much does concrete weigh?+

Roughly 2.4 tonnes per cubic metre. A modest 3 by 3 metre slab at 100 mm thick is nearly a cubic metre, so almost two and a half tonnes of material to place in one session.

Do I need reinforcement mesh?+

For thin domestic slabs on a well-prepared sub-base, often not. Mesh is normally specified where the slab carries vehicles, spans variable ground, or where crack control matters, and its position within the slab depth is what makes it effective.

Related calculators

What typical jobs need, and how depth changes it

These rows use the same formula as the calculator: volume = length × width × depth × (1 + waste), weight at 2,400 kg/m³, and bag counts from the yields on this page (0.011 m³ for a 20 kg bag and 0.0138 m³ for a 25 kg bag).

Typical jobs at 10% waste
Jobm³ (net)m³ + 10%Tonnes20 kg bags25 kg bags
Garden path 5 m × 0.9 m × 75 mm0.340.370.93427
Shed base 3 m × 2.4 m × 100 mm0.720.791.97258
Patio slab 4 m × 3 m × 100 mm1.201.323.212096
Strip footing 10 m × 450 mm × 225 mm1.011.112.710281
Driveway 6 m × 3 m × 150 mm2.702.977.1270216

The patio row is the page's own worked example: 1.2 m³ net, 1.32 m³ with waste, about 3.2 tonnes and 120 bags of 20 kg. At 1.32 m³ it sits inside the 1 to 2 m³ range that the page calls a genuine toss-up between mixing bags yourself and ordering ready-mix.

Depth is the number that surprises people

One 4 m × 3 m slab, changing only the depth
Depthm³ (net)m³ + 10%Tonnes20 kg bags
75 mm0.900.992.490
100 mm1.201.323.2120
125 mm1.501.654.0150
150 mm1.801.984.8180
200 mm2.402.646.3240

Going from 100 mm to 150 mm is only 50 mm, but it adds half as much concrete again: 1.2 m³ becomes 1.8 m³. Volume grows directly with depth. Check the depth first, because it is the dimension people most often guess.

Six mistakes when ordering concrete

  • Mixing up millimetres and metres. A 100 mm slab is 0.1 m deep. Typing 100 into a metres field gives a volume a thousand times too big, and typing 0.1 into millimetres gives almost nothing. Check the unit selector before you read the result.
  • Using zero waste. Ground is never perfectly level, formwork bows slightly, and some mix is left in the barrow. Running short mid-pour leaves a cold joint, which is far worse than having a little extra.
  • Treating the base as flat. If the sub-base slopes or is dug unevenly, the average depth differs from the nominal one. Measure at several points and use the average.
  • Mixing up bag sizes. A 20 kg and a 25 kg bag do not yield the same volume. Always count in the bag size you actually plan to buy, and check the stated yield on the packaging.
  • Forgetting the extras. Thickened edges, trenches around a slab and foundation steps all add volume that the plain length, width and depth do not capture. Add them as separate rectangles.
  • Rounding down. Always round up the bags or the ready-mix volume. Ordering too little is the expensive mistake.

Embed this calculator on your site

You can put this tool on your own page, blog or lesson site for free. Copy the code below and paste it into your page. Please keep the credit line under the tool. The embedded version shows no ads, loads no analytics and sets no cookies.

<iframe src="https://toolcorner.net/embed/concrete-calculator" title="Concrete Calculator" width="100%" height="1170" style="border:0;max-width:760px" loading="lazy"></iframe>
<p style="font-size:13px">Calculator by <a href="https://toolcorner.net/construction/concrete-calculator">Tool Corner</a></p>

Cite this page

If you use this tool in a report, assignment or article, you can cite it like this.

Tool Corner. (2026). Concrete Calculator [Online calculator]. https://toolcorner.net/construction/concrete-calculator

Concrete Calculator. Tool Corner. https://toolcorner.net/construction/concrete-calculator. Retrieved [date].

Assumptions & limitations

Every figure here comes from a simplified model. Keep these limits in mind when reading your result:

  • Assumes a rectangular pour of uniform depth — irregular shapes should be split into rectangles and added.
  • Bag yields are typical figures; check the manufacturer’s stated yield, which varies by product.
  • Weight assumes normal-weight concrete at 2,400 kg/m³.
  • Excludes reinforcement, formwork, sub-base and any over-dig.

Further reading

Formula & reference

This is an estimate, not a materials order

Quantities come from the dimensions you entered and the coverage rates listed in the assumptions above. Real coverage varies with substrate, porosity, application method, batch and weather, and no allowance here replaces measuring the actual space. Confirm every figure against the manufacturer’s data sheet for the specific product and your own site measurements before you buy, mix or pour.

Coverage rates and conversions on this page follow the sources listed below. The page has not been reviewed by a chartered surveyor or building-control officer. Read the full disclaimer.

Sources & references

Estimates only — always confirm quantities against the manufacturer’s coverage figures and your own measurements. General references:

  • Approved Documents — UK building regulations guidance for foundations and slabs
  • The Concrete Society, Technical Report 34: Concrete industrial ground floors (4th edition) — the UK reference for ground-bearing slab thickness and concrete specification
Found an error? Report it →
Last updated
Was this result right?
Found this useful? Share it
Help someone else find this free tool.